The West Kelowna council meeting on November 24, 2026 was my second as a councillor, and the first one where I read the whole agenda package the way I said I would during the campaign. It ran 61 pages: four main reports, six appointments, and the minutes from November 10. We met at 6:00 p.m. in Council Chamber at 3731 Old Okanagan Highway, open to the public and webcast live.

Here is how I read a package. For every report I want to know five things: what is being decided, what it costs, who it affects, when it happens, and what happens if it doesn't. Then for every number and every claim I keep asking "why" until the report stops answering. Wherever it stops, that is where my question comes from.

None of this is an accusation. Staff wrote these reports and most of what is in them is solid. The questions point at what a report shows and what it leaves out, so Council and residents can understand a decision before it is made. I wrote the questions before the West Kelowna council meeting, and I have added what I learned in the room under each one. Where a question is still open, I say so. Where I have done my own arithmetic, I say so and show the inputs.

Summary

What was on the agenda. Six council appointments, a development permit with one parking variance at 1835 Ross Road, a 20-year parcel tax so 38 Green Bay owners can pay for dredging, the sale of a 360.6 m² strip of Vancouver Road for $40,000, and the third update on the City's $2.1 million software replacement (ERP-HRIS), which is now forecast at $2,213,315.

Where I stand.

  • Appointments: no concerns.
  • Ross Road permit: I like this one. More commercial space for West Kelowna on a property that has sat unused for a long time. No neighbours responded to the notice, the creek will be monitored, and it passed unanimously.
  • Green Bay dredging: no problems. The people who benefit pay. The staff presentation answered everything I went in wanting to know, and the three readings passed unanimously.
  • Vancouver Road sale: no problems. It is an awkward strip of road the City doesn't need, the sale doesn't affect traffic, and the $40,000 is the appraised value.
  • Software project: necessary, not failing, and cheaper than Vernon's and Nanaimo's by a wide margin. Yes, it is 5.4% over budget. The new CFO found a $70,000 gap in the April forecast, and staff are working to negotiate the weekly consultant fee down. What I still want is the full cost to project close, a date for the tax and utility modules, and a plan for eBilling users.

The questions below were written before the meeting. The answers, where I got them, are underneath each one. Where I didn't need to ask, I say that too.

The routine items

Every West Kelowna council meeting opens the same way. Adoption of the agenda and the November 10 minutes were procedural, and I had no questions on either. One thing worth noting from the minutes: they record that Council received the Housing Target Progress Report by resolution, which is what the Provincial order requires. Good to see that done properly.

Council appointments

Items 5.1.1 to 5.1.6 appoint councillors to six outside bodies. I am appointed to the Okanagan Regional Library Board, with Councillor Da Silva as my alternate. I am looking forward to that one.

Item 9.1: Development permit at 1835 Ross Road

This is a multi-unit commercial building on a vacant lot near Mount Boucherie Secondary. The corner unit is a restaurant with a drive-through. The drive-through itself was approved earlier this year through a separate rezoning, so that part was not being decided at this meeting. The lot backs onto McDougall Creek, and single-family homes sit to the north and east.

Council was asked to issue the permit and approve one variance. It lets parking spaces sit closer to the property lines than the bylaw allows: 3.0 m from Pike Road and 1.5 m from the side boundary. The developer posts a $176,212.50 landscaping bond, and the roughly 180 m of new sidewalk and bike lane along the frontage is a bylaw requirement the developer has to meet.

I like this project. That lot has sat unused for a long time, it is next to the high school, and West Kelowna needs more commercial space. My questions were never about whether it should go ahead. They were about making sure the creek protection is funded and the neighbours were heard before the vote. Here is what I asked and what I learned.

  1. How many neighbours responded to the notice, and what did they say? Notice went to everyone within 100 m, and the report confirms that. It didn't say whether anyone replied. Answer: nobody did. No feedback came back from any of the surrounding neighbours.
  2. Is the creek restoration secured by a bond? The environmental consultant's report says a restoration estimate and bond "will be provided by others." The only bond in the permit covers landscaping. The consultant also calls for three years of monitoring after construction. Answer: no, it isn't. The creek will be monitored through construction and after. This is a well-known developer with a track record in West Kelowna, and I'm comfortable with that. The permit and the variance passed unanimously.

Item 9.2: Green Bay dredging and the Phase 2 parcel tax

Waterfront owners in the Green Bay area petitioned the City to dredge the mouth of the bay. Phase 2, the dredging itself, costs $722,609. The City pays $36,130, which the report describes as the equivalent of two parcels' shares. The other $686,479 is borrowed through the Municipal Finance Authority over 20 years and repaid by 38 property owners.

Each owner has a choice. Pay $18,065 up front between December 15, 2026 and February 28, 2027, or pay about $1,525 a year until 2046. Council gave the bylaw three readings at this meeting. Adoption comes later.

I have no problems with this one. It is a fair cost-recovery model: the people who benefit from the dredging are the people paying for it. What the owners need is clear numbers so they can choose between paying now and paying over 20 years, and that is all my questions were about. I went in with four of them. The staff presentation covered every one before I had to ask, so I didn't, and the three readings passed unanimously. If you own on Green Bay and want the detail, the presentation is in the webcast linked at the bottom of this post. Here is what I wanted to know going in.

Green Bay dredging parcel tax: pay up front versus pay over 20 years Two bars. Paying up front costs 18,065 dollars. Paying 1,525 dollars a year for 20 years costs 30,500 dollars, which is 12,435 dollars more. What one Green Bay parcel pays, by option Item 9.2, Phase 2 parcel tax. 38 parcels, bylaw gets three readings tonight. $18,065 Pay up front Dec 15, 2026 to Feb 28, 2027 $30,500 Pay $1,525 a year 20 years, 2027 to 2046 +$12,435 roughly 5.6% implied Bars start at zero. Figures from the November 24, 2026 agenda package; the difference and the rate are my arithmetic.
What one Green Bay parcel pays under each option. 20 years at $1,525 is $30,500, which is $12,435 more than the $18,065 up-front amount. My arithmetic from the report figures.
  1. What interest rate is the $1,525 a year based on? Twenty years at $1,525 is $30,500, which is $12,435 more than paying up front. That implies a rate of roughly 5.6%. That is my calculation from the two figures in the report, not a number staff gave. Owners have to choose by February 28, and the rate wasn't in the report.
  2. Why does the City pay two shares, and is that $36,130 in the 2026 budget? Taxpayers citywide are covering it. The report doesn't explain why two shares rather than one or zero.
  3. If some owners pay up front, does everyone else's annual charge go up? The bylaw allows the charge to change with "the number of parcels contributing" but doesn't say how.
  4. How long will the dredging last? The tax runs to 2046. If the bay needs dredging again before then, who pays?

Item 9.3: Vancouver Road partial closure and sale

Two homeowners at 1463 and 1469 Vancouver Road asked to buy an unused strip of road beside their lots: 360.6 m² in total, split 231.5 m² and 129.1 m². The City receives $40,000, which goes into the Land Acquisition Reserve. The sale lets 1463 subdivide into two lots and brings a long-standing encroachment from 1469 inside its own property line. Council gave three readings and directed staff to advertise, and the public can comment before adoption.

I have no problems with this one either. It is an awkward strip of road the City has no use for, the sale doesn't affect traffic, and the money goes into a reserve. My one question was for the record, because small sales of public land are exactly where residents should be able to see how the price was set.

  1. How was the $40,000 set? It works out to about $111 per square metre, by my arithmetic. No appraisal was shown in the package. Answer: $40,000 is the appraised value. That settles it for me, and I supported the three readings.

Item 9.4: The City's new software platform (ERP-HRIS), Update No. 3

This is the item at the West Kelowna council meeting I spent the most time on, and it was information only. No vote. It still gets the most attention from me for three reasons. It touches every resident, because it changes how you pay property tax and utility bills and adds a new online portal. It runs every City paycheque starting in January. And it has the most numbers in the package, and several of them either don't add up or aren't there.

What is being replaced

The City is replacing its decades-old finance, HR and payroll software, Vadim, with Oracle Fusion. It is also adding a new system called Ravic for property tax, utility billing, cemetery, cashiering and the new resident portal. Novamodus is the main implementation consultant, and Ravic is its sub-partner.

The timeline so far: the idea dates to 2021, it was budgeted in 2023 and launched in July 2024. The original go-live was October 2026, which moved to January 4, 2027. The Oracle finance, HR and payroll go-live is still January 4, 2027. The Ravic modules, the ones residents actually touch, are delayed to a target of "Q1 2027" with no date attached.

The numbers in the report

The approved budget is $2,100,000. The forecast is now $2,213,315. Ongoing subscriptions will run $377,616 a year.

See how West Kelowna's cost compares with Vernon and Nanaimo →

Two things stood out when I checked the math. First, the report prints the overrun as 0.5%. By my arithmetic it is 5.4%: $113,315 divided by $2,100,000. Second, the project was forecast under budget in the April update. It is now $113,315 over, which is a swing of roughly $127,000 in seven months, and the report doesn't say what changed. I got the answer at the meeting: about $70,000 was missing from the April forecast. The City's new CFO found the error when she joined the project. That is exactly what you want a CFO to do, and she deserves credit for it.

Then there is the consultant fee. Novamodus will charge $6,200 a week from January 1 until Ravic goes live. That is about 20% more than the $5,167 a week negotiated for the last extension, and it is not in the $2,213,315 forecast. Thirteen weeks, to the end of Q1, is $80,600. Twenty-six weeks, to the end of Q2, is $161,200.

West Kelowna council meeting November 24, 2026: ERP budget versus forecast Four bars. Approved budget 2,100,000 dollars. Current forecast 2,213,315 dollars. Forecast plus 13 weeks of the 6,200 dollar weekly Ravic fee, 2,293,915 dollars. Forecast plus 26 weeks, 2,374,515 dollars. The last two are my estimates. ERP-HRIS project: approved, forecast, and what is not counted yet Item 9.4, Update No. 3. Right two bars add the $6,200 weekly Ravic fee from January 1, 2027. $2,100,000 Approved budget $2,213,315 Forecast 5.4% over $2,293,915 +13 weeks to end of Q1, my estimate $2,374,515 +26 weeks to end of Q2, my estimate Bars start at zero. Dashed line is the approved budget. Hatched bars are my arithmetic (forecast + weeks x $6,200), not a staff forecast. Term staff after go-live are not included in any bar because the report gives no figure.
Approved budget, current forecast, and what the forecast becomes if the $6,200 weekly Ravic fee runs 13 or 26 weeks past January 1. The two right-hand bars are my arithmetic from the report figures, not a staff forecast.

My eight questions on the software project

  1. Can the milestone table show the original target beside the current date? The column is labelled "Target / Actual" but shows one date per milestone. Without both, nobody can see how far each step has slipped.
  2. The project was forecast under budget in April and is now $113,315 over. What changed? A swing of roughly $127,000 in seven months, and the report does not explain it. Answer: about $70,000 of it was a figure missing from the April forecast, caught by the new CFO.
  3. Why is the new weekly rate $6,200 instead of $5,167, and is there a cap? An open-ended weekly fee with no cap is a real budget risk. Answer: the City is working to negotiate the rate down, and to speed up the Ravic timeline so fewer weeks get billed at all. Both are the right moves. I will be watching for the number.
  4. When will Council see the confirmed Ravic date and the total extension cost? Every week of delay costs $6,200. The report promises both "prior to the next update" but gives no date.
  5. What is the full forecast to project close, including the Ravic fee and term staff past go-live? The report says term positions continue after go-live but gives no cost beyond the $275,000 already budgeted.
  6. About 1,750 staff hours went into two early training stages alone, and regular staff time isn't costed. What work has been deferred to make room? The report says real staff time runs higher than that figure. Thirty-three City staff are now on the cutover team, mostly on top of their regular jobs. None of that regular time appears in the budget. It comes from somewhere, which means other work waits.
  7. What will this system save in time or money over the next five years? The City will pay $377,616 a year in subscriptions. The report lists features and better reporting, but no savings figure.
  8. Pre-meeting: how many accounts are on eBilling now, and what is the target for re-subscribing? Everyone on eBilling has to sign up again in the new portal to keep getting bills electronically. The report gives no count and no plan for residents who miss it. For most residents, this is the most visible part of the whole project.

How West Kelowna compares with Vernon and Nanaimo

I want to be fair here, because the picture is better than the questions above might suggest. Replacing a 40-year-old system is necessary. The project is not failing. And compared with other BC cities doing the same thing, West Kelowna is getting this done for less.

Vernon is another Okanagan city replacing Vadim. When its council approved the project in 2022, staff recommended up to $3,095,689 to implement and up to $594,013 a year in ongoing costs. That is from Castanet's report on the Vernon council decision. West Kelowna's forecast is $2,213,315 to implement and $377,616 a year. That is roughly $882,000 less up front and about $216,000 less every year, by my arithmetic. Credit where it is due.

Nanaimo's ERP budget rose by $1.9 million to $5.1 million in 2025, as NanaimoNewsNOW reported. The reasons will sound familiar: staff stretched between daily work and the project, a one-year extension, and licensing costs during the delay. Those are the same risks I am asking about in questions 3 through 6.

ERP implementation cost: West Kelowna compared with Vernon and Nanaimo Three bars. West Kelowna forecast 2,213,315 dollars. Vernon approved up to 3,095,689 dollars in 2022. Nanaimo revised budget 5,100,000 dollars in 2025. ERP implementation cost, three BC cities West Kelowna is the lowest of the three, before and after its overrun. $2.21M West Kelowna 2026 forecast $3.10M Vernon 2022 approved, up to $5.10M Nanaimo 2025 revised budget Bars start at zero. Sources: West Kelowna agenda package Nov 24, 2026; Castanet (Vernon, 2022); NanaimoNewsNOW (May 2025).
Implementation cost of ERP projects at three BC cities. West Kelowna is the current forecast; Vernon is the 2022 approved maximum; Nanaimo is the 2025 revised budget. Sources linked in the text.
City Implementation Ongoing per year Status
West Kelowna $2,213,315 forecast $377,616 Finance, HR, payroll go live January 4, 2027. Tax and utility modules "Q1 2027"
Vernon Up to $3,095,689 Up to $594,013 Approved 2022
Nanaimo $5,100,000 revised Not stated in source Budget raised $1.9 million in 2025, one-year extension

Camrose, Alberta is the closest match on sequence. Its October 2025 council highlights say the finance and HR system went live October 1, 2025 and the tax and utility software was set to follow on December 1. The City's March 2026 notice to residents says the new bill format started that month, with the online portal still to come later in 2026. So the resident-facing piece landed after the back-office piece there too. West Kelowna's own risk register rates Ravic as High for being "untested in BC," which is the same kind of risk.

This is normal for ERP projects, not an excuse, just context. Panorama Consulting's 2012 ERP Report, as summarized in PMI's PM Network, found 56% of implementations over budget and 54% over schedule. Its more recent data, as summarized by Spendesk, puts the median implementation at 15.5 months, with roughly two in five organizations over budget and about 39% finishing late. Those are second-hand figures, so treat them as approximate. West Kelowna launched in July 2024 and goes live in January 2027, which is about 30 months by my arithmetic, longer than the median and in line with what Nanaimo and Camrose went through. Against that backdrop, a 5.4% overrun on a budget at the low end of its peers is a good result. My concern is narrower than "the project is over budget." It is that the forecast leaves out costs the report itself says are coming.

What I would like to see

Three things. The full cost to project close, including the weekly Ravic fee and term staff after go-live, so Council and residents can see the real number. A firm date for the parts residents actually use, the tax and utility billing and the portal. And a plan for the eBilling re-subscription so nobody quietly falls back to paper because they missed an email.

How to catch up on the West Kelowna council meeting of November 24, 2026

The meeting ran at 6:00 p.m. in Council Chamber at City Hall, 3731 Old Okanagan Highway. If you missed it, the recording is on the City's webcast page, and the full agenda package and, once adopted, the minutes are on the City's council calendar. The next regular meeting is Tuesday, December 8, 2026.

If you want the background on how I got here, my post on the November 10 council meeting covers the orientation and training. My earlier post on the West Kelowna property tax cut is a decent primer on how the tax side of the City's finances works.

Reach out

I will keep updating this post as the open questions from the West Kelowna council meeting get answers, especially on the software project. If you live near Ross Road, own on Green Bay, or you are one of the eBilling accounts that will need to re-subscribe, I would like to hear from you. The contact page is the fastest way to reach me.